Arrange in correct sequence the actions involved in reenergizing machines.
(i)
Energize the machine and continue with positioning or testing.
(ii )Make sure no employee is exposed to the machine. Clear all employees from the area around the machine.
(iii) Remove the lockout/tagout devices.
(iv) Clear materials and tools from the machine.
(v) De-energize the system: isolate the machine from its energy source.
(vi) Reapply energy control procedures in case additional maintenance or service is required.
- (A) (i), (ii), (iii), (iv), (v), (vi)
- (B) (vi), (v), (iv), (ii), (ii). (i)
- (C) (iv), (ii), (iii), (i), (v), (vi)
- (D) (iii), (ii), (iv), (i), (v), (vi)
Give me a hint
Hint:
Step (vi) is the last action to be performed.